The Salerno prosecutor's office ordered the urgent preventive seizure of part of the Salerno-Reggio Calabria high-speed rail construction site, Lot 1A Battipaglia-Romagnano, in Campagna, according to Il Mattino.

The order also covers the area used to store excavated earth and rock. A separate sector of the site was excluded after checks reported no anomalies in its discharge system.

The investigation began after reports of abnormal clouding in the Sele. Investigators traced runoff from site surfaces to the Trigento stream, a tributary of the Sele, reporting that water reached the watercourse without the planned purification treatment.

Along the Trigento they documented fine, whitish sediments spreading toward its confluence with the Sele and downstream stretches. Inspectors, supported by ARPAC, reported differences between the installed collection and discharge systems and those in the authorised documents, plus sludge build-up in the first-rain water system.

The storage area allegedly lacked systems to regulate and contain rainwater runoff. The alleged offences remain under preliminary investigation, and the decree must go before the judge for preliminary investigations for possible validation. Final ARPAC test results have not been released, and no definitive criminal responsibility has been established.