Undersecretary Tullio Ferrante has outlined the current status of the main road infrastructure projects in the Sannio area, with progress reported on the SS372 Telesina, the planned Caserta-Benevento motorway axis and several bypasses in the Fortore area.
The Caserta-Benevento motorway axis has entered the updated agreement between the Ministry of Infrastructure and Transport (MIT) and ANAS, according to the report. A feasibility document has been prepared and transmitted to the ministry for the next stage of project development.
On the SS372 Telesina, work is divided into two lots. The first lot, between San Salvatore Telesino and Benevento, has completed executive design and is now awaiting environmental verification before approval. The stated objective is partial delivery of a first construction section by the end of 2026, followed by complete delivery of the works in January 2027.
The second Telesina lot, between Caianello and San Salvatore Telesino, has completed the Services Conference and is undergoing final activities toward definitive project approval.
Works are ongoing on the SS212 Val Fortore bypass at San Marco dei Cavoti, with completion expected by December 2027. The bypass at San Bartolomeo in Galdo remains in the environmental authorization process, alongside the procedure for the SS369 Appulo-Fortorina.
The timelines and procedural updates were reported by NTR24 on November 11, 2026, citing Ferrante, and have not been independently confirmed against current MIT or ANAS records. No project costs, contract values or detailed construction schedules were provided in the report.