A further inspection is under way at the former Garigliano nuclear plant to compare the new labels on radioactive-waste containers with the material actually inside them, according to Il Mattino.
The inquiry concerns alleged failures in the characterization and labeling of radioactive-waste drums stored in the former Diesel deposit at the plant in Sessa Aurunca.
Five people have been reported as under investigation for alleged false statements in a public document and aggravated fraud. The allegations have not been established by a final judicial decision.
The former Diesel deposit is an active temporary radioactive-waste storage area. Sogin reports 957 cubic metres stored there as of 31 December 2025, out of 2,654 cubic metres of radioactive waste held at the Garigliano site on that date.
Sogin says decommissioning work at Garigliano includes dismantling the old Radwaste system, with contaminated components handled using upgraded monitoring systems and remote-controlled cutting robots. Sogin began that dismantling work in April 2025.
The outcome of the latest inspection and the verification of the drum contents has not been announced. Sogin’s published storage figures do not resolve the specific allegations concerning the inspection records or subsequent labels.
It is not established whether any mislabeled drums caused a radiological release or exposure. ISPRA’s radiometric campaign from June 2013 to January 2014 found radioactivity concentrations within regional and national variability and did not identify a radiological concern in the surrounding territory at that time, but that survey predates the alleged events.