Fonderie Pisano has presented a new project for its Fratte plant centered on the existing electric furnace rather than the previously proposed three-furnace configuration, according to Il Mattino.

The revised plan removes the coal-fired furnaces, avoids new construction and eliminates the department producing thermosetting-resin cores.

The three-furnace applications were withdrawn following discussions with regional authorities and the Ministry of Enterprises and Made in Italy.

The proposed configuration would cut authorized production capacity by more than 80% and is expected to require fewer workers than the three-furnace project. The final number of workers who could return has not been specified.

Institutional and union discussions link any temporary reduced restart at Fratte to a longer-term reorganization, new investment and a possible relocation to another industrial site.

The company said it would seek extraordinary wage-support measures connected to partial cessation of activity instead of proceeding immediately with collective dismissals.

The Campania Region has not yet granted the new Integrated Environmental Authorization, so the restart date remains unresolved.