Salerno mayor Vincenzo De Luca has criticised the administrative delays holding up funds for work at the Stadio Arechi and Campo Volpe, describing the procedure as a “palude burocratica”. According to Il Mattino, De Luca linked the slowdown to the handling of the funding.

At issue was a CIPESS decision approved almost two months earlier. According to Il Mattino, the mayor said the papers had still not reached the Corte dei conti.

The article reported work at the Arechi and Volpe sites was continuing despite the funding bottleneck. It put the allocation for Arechi and Volpe at 140 million euros.

The wider project covers the complete restructuring of the Arechi, a new sports facility replacing Campo Volpe, and construction of the new Pala Tulimieri, according to the Comune di Salerno. The Comune said work at Campo Volpe and Pala Tulimieri had started on 25 July 2025.

Work to restructure and modernise the Arechi began on 21 November 2025 with the demolition of the Curva Nord, according to the Comune.

The Arechi plan includes a full roof with a photovoltaic system, work on the stands, new hospitality areas, skyboxes, vertical connections, a visiting-supporters sector and a Salernitana museum, according to the Regione Campania project document.

Funding figures and timetables reported publicly do not fully align. The Comune indicated 120 million euros from the region for the new Arechi, while Il Mattino reported 140 million euros for Arechi and Volpe. The regional document set delivery of the works by December 2025.

It is not known whether the Court of Auditors stage was completed after the article was published. It is also not known whether the December 2025 delivery date was met, and the acquired sources do not explain whether the funding gap reflects different project boundaries. No updated, detailed completion dates for Campo Volpe were available in the acquired sources.