The club says rainwater is leaking through the stand and into the rooms underneath the San Clemente baseball stadium in Caserta. According to Il Mattino, club president blames an unrepaired canopy and a missing gutter.

The club says the leaks could affect the venue's suitability and its entry into the 2027 men's national Serie C championship. That outcome is not verified, and no independent technical assessment of the cause or severity has been reported.

The redevelopment was funded with 500,000 euros from the PNRR. The planned work covered the 1,500-seat stand, locker rooms, systems, roofing, fencing and ironwork, according to local coverage.

The project is described as incomplete or suspended, with a substantial share of the work not carried out. Reported payments stood at 147,276.18 euros in the third quarter of 2025, or 29.46% of the funding.

In 2024, the Comune or those responsible for the works said restoration of the reinforced concrete had been completed, with work on the roofing and locker rooms to follow.

The San Clemente ground also serves as a meeting place for young people and families. The Comune has not issued an updated response to the club's complaints.